GEPCO Online Application for New Connection In 2024
GEPCO Online Application for new connection In 2024 Along with the growing population.
The construction of new houses is also increasing, Which is also the need of time.
There are two ways to get a new electricity connection in Pakistan.
Most people do not know what is the process of the GEPCO online application form for new connections. How to fill the form and which documents are required for a new connection.
GEPCO Online Application for new connection
We are here to help you out of this situation. Don’t worry; stay relaxed. There is a step-by-step guide on how to apply for an online Gepco new connection, as well as a manual way.
You can demand a new connection by staying at home, and that’s all that is possible with the GEPCO online application system, which allows to you apply for a new connection from home, and it consumes less time and effort.
There are single-phase (under 15 kw or 15000 watts) and second is Three phase (above 15 kw )connections available for domestic users.
First, you have to choose your requirement if you have built a small house or are not a home appliances user, Then you should select a single-phase connection. And if you have heavy consumption, you should go for a Phase connection.
Also, Check your GEPCO BILL
GEPCO New Connection Procedure.
There are two ways to get a new GEPCO connection. One is visiting the sub-divisional office manually. The second is the Gepco online application portal website.
The oldest and most traditional of the two is the manual method. To get a new connection, visit the nearest GAPCO office and fill out a new connection form. Make sure to provide the necessary information while filling out the form.
- Name, address, phone number, etc., of the recipient of the new connection.
- After filling out the form, attach a copy of the identity card and the title deed of the place along with the form.
- If you do not own the premises or house, attach the Owner’s Permit on stamp paper along with the proof of Ownership.
- The next step is to submit the documents to the Sub-Divisional Office. The office representative will give you a receipt after checking the documents.
GEPCO Online Application For New Connection
Now it is easier than ever. GEPCO has made a user-friendly portal where you can register a new connection in just minutes. How to apply for gepco online application Here is a step-by-step guide.
First of all, get the required documents to achieve a successful output. 1, neighbor GEPCO bill copy. 2, Property ownership document copy. 3, attested ID card copy. 4, attested ID Card copy of witness and a wiring test Report.
Click the button it will redirect to the ENC Official website.
- Just go to ENC’s Official website.
- You’ll notice different boxing like Track, Apply, Change, Print Form, etc.
- Click on the apply box to apply Gepco’s new connection. After clicking you’ll see a form that asks for information about Sub-Division.
- Select the category type. After selecting, a new form will appear below it.
- In this form, you need to specify your connection type, furnish details regarding the applicant, provide information about the contact person, describe premises details, and attach all the necessary documents.
- Ensure that you attach the following scanned documents in JPEG format:
- Copy of Property Document
- Attested CNIC Copy of the Applicant
- Attested CNIC Copy of the Witness
- Copy of the Neighbour’s Electricity Bill
- Wiring Contractor’s Test Report
- Lastly, please check the “I Agree” box and proceed by clicking the “Submit” button to complete your application.
GEPCO Online Application Status
For consumer Gepco have a portal named “Track”. You can check your application status by entering your CNIC Number or Tracking ID which Gepco has provided at the time of submission of the application.
- Simply Go to ENC WEB Portal
- and click on the “Track” Box
- Select “New Connection” in the application type.
- Enter the Service provider name such as GEPCO.
- Just Enter your CNIC or Tracking ID number.
- Click on the “Submit” button.
- Now you will see your Application Status with a full details sheet.
GEPCO Demand Notice
Once the new connection application gets approved by GEPCO, they will issue a Demand notice to you. you have to pay a fee to install a new connection. The amount of Gepco Demand notice is around about 9000 to 12,000. It’s an estimated fee. they will install an electricity meter along with a 40-meter wire. If your house is far away from the electric point then you have to pay for an extra wire price.
Conclusion:
After reading this article we hope you will be able to get a new connection from GEPCO. All the guides are given step by step.
اسلام علیکم و رحمۃاللہ وبرکاتہ جی میں نیا میٹر لگوانا چاہتا ہوں
Axha g
wasy mashwra ha k 24 hazar meter ka aur bad ma bill bhe deny sy acha ha k chota mota Solar setup lagwa len.
Assalamualaikum Bhai g m ne new conection karwana h .plz help me
rishwat ka bazar garam he 1kilowatt ka 45 hazar dia he me ne lalamusa me wapda oficer kehta he agar pesy nahi do ge to sari zindgi meter approval nahi donn ga pesy adaa kar diy phir bi meter nahi lagaa raha
koi sunny wala nahi
سر میں نے نیو میٹر کے لیے درخواست دی ہے پر وہاں پر جو لائن مان ہے وہ مجھ سے 17 ہزار روپیہ رشوت مانگتا ہے میں نے سنگل فیز میٹر لگوانا ہے جو بھی قانونی طور پر پیسے بنتے ہیں وہ میں ڈیمانڈ نوٹس کے بعد وہ میں جمع کرواؤں گا
سنگل فیز نیو میٹر کی کتنی سرکاری فیس ہے بتا دیں اور آج اپلیکیشن دیں تو کتنے دن میں میٹر لگ جائے گا۔
I want to install a new meter
Main new connection lagwana chahta hon plz sir help me